City staff are looking at ways to trim the budget for downtown Vernon revitalization after an unexpected cost increase. Infrastructure engineer Mark Dowhaniuk says spacing streetlights to match other areas, will increase the budget by about 200-thousand dollars. He says they'll know where that will come from once the tender price is finalized. "We would look at....There's a few items in the budget that we may remove from the budget," Dowhaniuk told city council. The two million dollar project will upgrade 30th Avenue from 33rd to 35th streets, similar to other blocks to the east.
-----------------------------
From the 2013 Proposed Financial Plan: 2013-2017 Proposed Financial Plan -P.420
Property owners $241,000 (LSA property owners)
Gas Tax reserve: $568,292 (Taxpayers)
Casino Reserve $864,708 (Taxpayers)
Ratepayers (Sewer) $403,000
Total $2.077,000