By Richard Rolke - Vernon Morning Star Published: February 17, 2012 1:00 AM
There will be no quick fix to repairs at the Vernon Recreation Complex. Requirements for selecting contractors and fabricating
the necessary equipment means about $1.7 million in construction could
take until late fall. “We hope to have everything done by November,” said Jim Coughlin, facilities manager. Damage has occurred to the pool walls and roof because
exterior finishing installed in 1993 failed and cold exterior air has
clashed with humid air from the pool. The dehumidification system was
also undersized when it was installed and it was shut off in 1998
because of costly repairs required to keep it running. The original heating lines in the auditorium are also
rotting out because they were not installed correctly when the complex
was built in 1965. As part of the dehumidification repairs, it could take
four weeks to advertise for and hire a mechanical engineer. That
engineer would then need six weeks to prepare a phase one report on the
project. It would then take four to six weeks to tender documents for potential contractors and then the tender period would be
three weeks. Coughlin anticipates that one week would be required to award a contract to a contractor. Actual construction could run from five to six months. The dehumidifier would be installed during the pool’s regularly scheduled shutdown from Aug. 27 to Sept. 17. “It takes four months to build the equipment,” said Coughlin. Tenders will also be issued for the pool’s roof and wall repairs and the auditorium heating system. RDNO directors had instructed staff to go to a request for proposals so a number of options for repairs can be considered.“I’m satisfied with the process established,” said director Doug Dirk.
No comments:
Post a Comment